Master Scheduler / Senior Project Scheduler, REPPERTTerminplanung, Oversea Wind Connection of Offshore Windpark Cluster „DolWin1“

START Date: 
August, 2011

I had to develop an integrated overall time schedule for the project. It has to integrate the partial projects and show the overall interactions, in-/outputs and the critical path. Therefore I created an schedule in MS-Project which shows summaries out of the detailed schedule from the partial projects.

After approve it and publish it to the costumer a routine had to be established to update the time schedule. Therefore I arranged fortnightly meetings with the partial project schedulers and we are able to discuss in the meeting upcoming issues and arrange actions.