PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection
START Date:
April, 2012 Project Planning, Executing, Monitoring & Control (Time, Scope & Cost)
- Review tender documents and prepare pre-contract planning package as per tender requirements
- Attend the Kick-Off meeting and discuss the Deliverables, Milestones, Concern & Risk Area, Permit to Work (PTW) and etc.
- Prepare Clause 14/8.3 (Baseline) Program, Project Planning Procedure / Packages and obtain approval from client/engineer & identify the Critical Path activities & forecast critical path on as-built schedule and notify to the Project Manager to control the variance.
- Issue 2 weeks Look ahead, 1 Month Look ahead program & Internal target program to meet the progress & minimize the variance to the project team
- Load resource & cost on the baseline program to monitor the resources, cost & progress.
- Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
- Prepare Progress Measurement System (PMS), Equipment Resource Planning (ERP), Manpower Resource Planning (MRP), Cost Control Registry (CCR) & Progress S-Curve (Early Start & Late Start)
- Update Progress Measurement System (PMS) daily, measure the progress performance from SV & SPI and report to the project manager for further action on the delay.
- Identify the delays and prepare the recovery program by crushing or fast track activities to achieve to maintain the baseline WBS completion date.
- Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
- Responsible to plan the most efficient way to complete the project as scheduled and within the budget I developed the Cost Control Registry (CCR) along with EVM system and update by monthly and assess the CV, EAC, ETC, VAC & CPI & submit the EVM report to Project Manager & Higher Management.
- Review the subcontractor baseline schedule and monitor the progress and responsibility to accelerate the progress to complete the on schedule.
- Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
- Identify the Project Risk, prepare the Risk Management Plan & monitoring the registry monthly basis
- Plan the 3 month project wise revenue for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
- Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I used update the cash flow as per as-build schedule.
Reporting & Closure
- Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
- Prepare & submit the EVM report to the management
- Prepare & submit daily/ weekly progress summary report to the management.
- Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
- Prepare and handle all planning documents for Project Closure.
- Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow
- Prepare the company cost report and analyse the annual revenue & profit/loss from the project control department.
ERP-Oracle-EBS
- Responsibility to create the projects in the ERP-Project Modules, task as per WBS, assign the customer & project manager and create the cost budget for the project
- Give instruction to Supply Chain user to select the proper Item Code and Task to avoid wrong cost booking.
- Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
- Develop new reports as when required and randomly Check the cost booked by finance department
- Highlight the ERP Project related issue to IT department
- Close the project as per close-out transmittals to avoid to book the cost on the completed project.
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
8000
Experience Hours (Forensic Analysis):
6000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: