planner/senior planner, pargar/paravan, Tunnel, Civil Projects
START Date:
August, 2005
END Date:
April, 2011 Responsibilities:
- Providing detailed work plans for different areas of the project and organizational & time management
- Planned and controlled project using Primavera® P3 and P6
- Reported progress of the project, Updated S Curve and compare to Planed S Curve, Critical way check for new decisions
- Reported program schedule periodically to project manager
- Cost control of project and prepare weekly report for project manager
Achievements
- Actual progress exceeded 60% after 9 months while desired planed progress was 52%
- Procurement never caused delay in construction because of prediction of it in activities and activity steps.
- The suggested sequence of construction of buildings in our program was dictated to other contractors performing similar project in other cities.
- Actual Returned Budget was equal to 60% of total cost while Time Progress was 50%.
- Company:
- Industry:
- Job Role:
- Project:
- Skills & Expertise: