planner/senior planner, pargar/paravan, Tunnel, Civil Projects

START Date: 
August, 2005
END Date: 
April, 2011

Responsibilities:

  • Providing detailed work plans for different areas of the project and organizational & time management
  • Planned and controlled project using Primavera® P3 and P6 
  • Reported progress of  the project, Updated S Curve and compare to Planed S Curve, Critical way check for new decisions
  • Reported program schedule periodically to project manager
  • Cost control of project and prepare weekly report for project manager

Achievements  

  • Actual progress exceeded 60% after 9 months while desired planed progress was 52%
  • Procurement never caused delay in construction because of prediction of it in activities and activity steps.
  • The suggested sequence of construction of buildings in our program was dictated to other contractors performing similar project in other cities.
  • Actual Returned Budget was equal to 60% of total cost while Time Progress was 50%.