PLANNING ENGINEER, AKTOR S.A., Development of ISF(military) Camp at Duhail, Qatar

START Date: 
June, 2015
  • Project – Development of ISF(Military) Camp at Duhail, Doha Qatar. (Scope includes 30 Gate Buildings, 18 Substations, 1 District Cooling Plant, 1 Sky diving training building, 1 VIP Main Gate, Boundary Wall and Pumping stations with Tanks).
  • Coordinate with all the (Civil and MEP) departments and prepare the Baseline program.
  • Issue monthly and weekly targets to Construction Managers/Site Engineers and prepare weekly progress layouts based on the progress acheived.
  • Update the program and prepare analysis reports (weekly & monthly). And issue the report to management and then to the client.
  • Prepare detialed program for critical issues and close monitoring.
  • Prepare Recovery programs for delayed targets with all resources and constraints.
  • Prepare the time impact programs for all the variation orders.