Worked as Project Control Engineer in
- Detailed Engineering of a LOP 3rd Gas dryer expansion project for M/s Lyondell Basel‘s La Porte site US.
- Detailed Engineering of Sulphuric Acid Plant II phase for M/s Mopani Copper Mines’s Zambia
- Detailed Engineering ofOffsite & Utilities, OPAL Petrochemical Projects, Dahej, and Gujarat.
Responsibilities:
- Assist Project Manager in preparing Project Execution Plan (PEP)
- Preparation of Project Schedule
- Establishing Internal Mandate - Generating discipline wise Document Delivery Schedule (DDS) & get it signed off
- Develop discipline wise Functional Schedule & Manpower Forecasting & Leveling based on the schedule dates & get it signed off
- Established progress measurement of project. Prepare and update Engineering “S” Curves and create forecast, Activity list catch up plan
- Preparing invoice as per the payment milestones & follow up for payment.
- Maintaining DCN & PCN Log
- Maintaining Risk Register
- Prepare Periodic Project Progress report highlighting areas of Concerns ,variance, Lag analysis & productivity for higher level management
- Follow up with discipline engineer for release deliverables as per schedule.