  • ENGRO New Ammonia – Urea Plant:

TKLS Project for the construction of a fertilizer complex consisting in two plants: the first one for the production of 2,194 MTPD of Ammonia using the technology licensed by Harold Topsoe A/S and the second one for the production of 3,835 MTPD of prilled Urea using Snamprogetti S.p.A technology. Client: Engro Chemical Pakistan Limited, Country: Pakistan

 

  • SAMIR Upgrade Refinery Project:

TKLS Project to upgrade the existing refinery in Mohammédia principally by the installation of a new processing complex and offsite and utility systems. This complex includes a VDU, a Hydrocracker to upgrade heavy oil to middle distillates and a Hydrotreater to produce low-sulphur diesel fuel. Client: SAMIR,Country: Morocco

 

  • Isocracker plants and other Units:

Project performed to build a new Isocracker Unit in the existing Refinery in San Nazzaro dè Burgondi (Pavia – Italy), using Chevron technology (BEDP – Process Engineering Design Package) to upgrade heavy oil to middle distillates, plus a new Solvent Deasphalting (ROSE) and interconnecting plant. Client: ENI S.p.A Divisione Refining & Marketing

 

  • Ferrara Combined Cycle Power Plant:

TKLS Project for Ferrara Combined Cycle Power plant, including 2 trains each composed of one gas turbine (ALSTOM technology) and one steam turbine generator plus one heat recovery steam generator. Client: Enipower

 

Activities:

  • Preparing and monitoring the Eng & Procurement detailed network schedule (Level III and Level IV Front-End 90 days)
  • Critical path analysis/recovery plans
  • Preparing and updating a calculation model as a method for the physical progress measurement of engineering
  • Preparing Project Control/Planning procedures
  • Editing Weekly and Monthly Progress reports
  • Analysis of trend
  • Expected Invoice schedule
  • Preparing Project Structures activities (WBS, OBS) with the associated resource and cost budgets
  • Issuing status reports by means of SAP/IBIS and EDMS systems.