Planning Engineer, BUTEC SAL, Electricity Capacity Expansion Ph.VIII

START Date: 
December, 2007
END Date: 
August, 2009

v  Visited the project site regularly for periodic progress report and evaluation.

v  Worked with Project Manager for support in the productive and timely completion of the project.

v  Provided BOQ of major projects to Bids Team for preparation of tenders. Projects tendered include NDIA C-II Airline Support Facilities (Doha), Developpement du Champ de Rhourde Nouss (Algeria).

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
2800