Planning & FEDC Engineer, Descon Engineering Limited Pakistan, DG Cement Plant, Kalar Kahar, Punjab, Pakistan
START Date:
April, 2004
END Date:
June, 2007 Worked on DG Khan Cement Khairpur, Chakwal, Pakistan
DG Cement Project involves 4500 Tons of equipment fabrication and erection, having overall 3 Million man-hours.
RESPONSIBILITIES
- Prepare and ensure master program of works / critical milestones are achieved and ensuring effective planning and monitoring of site progress and take corrective actions / recovery program to arrest slippages
- Revisits master schedule plan prepared at the bidding stage, after award of contract, in close co-ordination with Construction Managers and Site Manager.
- Follows up customer or engineering company for delivery of drawings as per agreed schedule.
- Ensures that Field Engineers raise and follow up Technical Queries with customer.
- Ensures that Planning Engineers prepare and distribute 3-months and 4-week look ahead schedules to Discipline In-charges Discipline Engineers and Material Controller.
- Updates and monitors Level-III plan keeping in view overall master schedule.
- Regularly performs critical path analysis, anticipates bottlenecks and highlight these to Site Manager and Construction Manager.
- Generates and analyzes standard reports related to progress and efficiency on daily, weekly and monthly basis.
- Ensure that extra work is properly estimated and monitored and that subcontract work progress is included in the overall scheme.
- Prepare/ Verify invoicing and billing formalities in Co-ordination with Project manager and Quantity surveyor. Preparation of Cash flow for the secured projects in co-ordination with Project Manager and Finance personnel.
- Prepares Project Windup Report at completion of the project.