Construction Planner, Bateman Engineered Technologies, DMO Coal Project
START Date:
September, 2009
END Date:
August, 2010 BATEMAN ENGINEERED TECHNOLOGIES (28/09/2009-27/08/2010)
SENIOR PLANNER
DMO Project Emalathleni (Construction & Commissioning)
- Schedule site activities and track their progress.
- Capture all expenditures, actual cost and schedule the IOP’s for the construction phase in order to maintain the cost and schedule report.
- Integrate the budget and the schedule using the WBS and CBS to forecast a reliable cash flow and determine the CPI and SPI for the monthly report.
- Manage the master schedule for Bateman
- Perform contractors claim verification.
- Develop the commissioning plan.
- Maintain the commissioning plan.
- Attend progress meeting with the client(BHP Billiton)
- Measure and report on earned value to the project manager and the client.
Reason for leaving: was offered a permanent position as forensic planner at Genrec
Experience Hours (Planning & Scheduling):
100
Experience Hours (Cost Management):
50
Experience Hours (Forensic Analysis):
50 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: