Senior Planner engineer, Vinci Contruction Grands Projets, Lusail LRT

START Date: 
November, 2009
END Date: 
December, 2009

 

Construction of the time schedule of Lusail Railway Transit System:

 

  • Establishment of the Work Breakdown Structure (WBS=GBSxPBSxABS);
  • Creation of the time schedule of the project (3000 tasks), Gantt & trip diagrams, in the time allowed (40 days).