Project Planner, Balfour Beatty Management, Ensus Bio-Ethanol Plant

START Date: 
January, 2009
END Date: 
October, 2009

- Initial Construction programme for the E & I installation to be created within a strict deadline for client

- Development of Electrical and Instruments database for all site activity enabling weekly reports to be more efficient.

- Day to day schedules for supervisors.

- Standard planning practice: Critical Path Development, S Curve analysis, Histograms, Baseline Comparison, progression reporting, end date improvement.

- Material Take-off assistance with QA, enabling the building of Job Card System for project in coordination with job norms and expectancies