Project Engineer (Civil), FURNACEFABRICA, India, India, Turn Key COPPER REFINERY PROJECT, Project Sulfuric Acid Plant (800 TPD), Client: Rashtriya Chemical Fertilizers, Bombay, Consultant: FEDO (Cochin)

START Date: 
December, 1990
END Date: 
March, 1992

Planning, Scheduling and Cost Control of projects; right from Study, Design stage, Contracts and Execution stage.