Senior Planning Engineer, Shimizu, Taisei, SK E&C, Mass Rapit Transit Project - Construction of Station and Tunnel
CAREER HISTORY
1) SK E&C (Singapore Branch)
(Downtown Line MRT Stage 3 Contract 930 – Singapore)
Contract Value – SGD 106.7 millions
Planning Engineer / Scheduler (May 2011 – Present)
- Preparation of Baseline Programme including the cost loading, resource loading, progress and cashflow S-curve for the project based on the Client’s working drawings and specification. The project is awarded on 01 April 2011.
- Preparation of Montly Progress Report (including Progress Photograph) for submission to the Client.
- Progress update and weekly monitoring of the progress and updating Project Critical Path
- Monitoring and Analysis of Project Critical Path
- Providing Catch-up schedule for construction works.
2) Shimizu Corporation
(Downtown Line MRT Stage 1 Contract 905 - Singapore)
Contract Value – SGD 102.7 millions
Snr Planning Engineer (Sep 2007 – Apr 2011)
- Preparation of Project Baseline Programme including the cost loading, resource loading, progress and cashflow S-Curve
- Progress updating and preparation of 3-month rolling schedule and monthly reporting to Client (LTA)
- Liaise with site managers and subcontractor for the preparation and maintenance of weekly schedule
- Preparation of necessary follow up schedule such as interface schedule with other contractors and GP Formula 1 organiser, catch-up programme, etc.
- Assist in providing necessary information to substantiate claims and EOT.
- Monitoring and updating tunneling progress and datas
- Preparation and updating of Risk Assessment for the project.
- Provide baseline programme for several tender submissions.
3) Taisei Corporation
(Circle Line MRT Stage 4 & 5 Contract 854 - Singapore)
Contract Value – SGD 391 millions
Senior Engineer (Nov 2006 – Aug 2007)
- Preparation and maintenance of method statement for construction of station and cut and cover tunnel
- Progress reporting for weekly and monthly updates as well as feedback for Monthly Report for submission to Client
- Preparation and update of construction schedule.
- Liaising with Consultants to solve technical problems
- Coordination for Permit to Excavate and Temporary Works
4) SembCorp Engineers & Contractors Pte Ltd
Project C856 – MRT Circle Line Stage 5
Civil Engineer (Aug 2006 – Nov 2006)
Contract Value – SGD 335 millions
- Assisting Design Manager in Consultant’s coordination matter, technical issues and queries, etc.
- In charge of shop drawings preparation and checking for diaphragm wall construction for 5 MRT stations
Project C422 – Kallang Paya Lebar Expressway
QA/ QC Engineer and Instrumentation Engineer (2002 – Aug 2006)
Contract Value – SGD 257 millions
- Overall control of all QA/QC matters.
- Preparation, monitoring and ensure the implementation of Quality Plan and Quality Management System.
- Liasing with Company Quality Assurance Department on quality issues.
- In-charge of Drawing Issue and Control and maintenance of controlled documents.
- Preparation and maintenance of construction method statements and material submission.
- In-charge of Instrumentation and Monitoring
- Assisting Design Manager in consultants’ coordination matters & some technical issues, technical queries, submission of Permit to Excavate, etc.
- Prepared Monthly Progress Report for submission to Client
- In-charge of as-built submission to Client
- Internal auditor for the company.
4) Kumagai – Sembawang – Mitsui Joint Venture
(North East Line MRT C705 - Singapore)
Civil Engineer (Aug 2000 – 2002)
- Material quantity (especially for reinforcement bar) calculation, ordering & issuing. Provide re-bar bending schedule & details.
- Metal or timber formwork & falsework system design and arrangement.
- Construction concept & method statement preparation & submission to client (LTA).
- Study and understanding Architectural & Structural drawings.
- Preparing the schedule and progress report system, i.e. Two weeks rolling schedule, Weekly Progress report and Monthly Progress report.
- Preparation and submission of the structural plans to Authority
- Preparation and submission of as-built drawings to Authority and Client (LTA).
- Coordinating with Structural Professional Engineer and Accredited Checker.
- Towards end of project, took over the Public Relation task and work involved such as entertaining complains and enquiries from Town Council and residents.