Maintenance Engineer, Transfield Worley Ltd, Woodside Energy Maintenance Management Project
START Date:
January, 2002
END Date:
November, 2002 Woodside Energy Maintenance Management Project
- Maintenance Engineer
Employed in the role of asset specialist in the rollout of SAP-PM to replace MCP, the Woodside legacy maintenance planning system. Responsibilities included:
· Rationalise and align facility technical data profiles and defining unified master class characteristic sets
· Develop data mapping table to enable migration of MCP Facility data to SAP-PM characteristics
· Interpret P&ID Drawings to create Functional Location Hierarchy within SAP-PM
· Assist in development, produce and deliver training material for SAP-MCC project data upload application
Experience Hours (Planning & Scheduling):
100 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: