November, 2013 - Created Work Breakdown Structure (WBS), input project activities, determined activity durations, and logic relationships.
- Prepare and update project schedule based on the contract.
- Created milestones to identify the start of work including activities that required constraints.
- Monitored and updated project progress on a routine basis against established scope, schedules and budgets
- Monitor critical activities based on the project schedule and advise project management.
- Monitor day to day work progress and prepare the weekly and monthly program and report.
- Maintain and record update of site work progress obtained from Project Manager.
- Prepares monthly report reflecting work progress summary.
- Report to the Project Manager about the current work progress and make comparison between
plan and actual progress and study impact of alternative approaches to work. - Participate in project meetings and discussions with the Client as required.
- Assists in preparing work program, cash flow and manpower histogram for tenders.
- Performs other duties and responsibilities as may be assigned from time to time.
- Ensure Oracle database systems operate efficiently and securely.
- Set work program and target milestones for each phase based on the project plan.
Experience Hours (Planning & Scheduling):
18200
Experience Hours (Cost Management):
10850
Experience Hours (Forensic Analysis):
9650 - Company: