Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

3 years as a Project Engineer, Al-Mohanna Trading & Contracting Co., Road Improvement Works In Rayyan Area Phase-04

START Date: 
March, 2014
END Date: 
December, 2016

·         Visited project sites during construction to monitor progress and consult with contractors and on-site               engineers.

·         Supervised other engineers and technicians.

·         Coordinated with drafts-persons and technicians to transform designs to working drawings.

·         Inspected project sites to monitor progress and adherence to design specifications, safety protocols and           state sanitation           standards.

·         Estimated quantities and cost of materials, equipment and labour to determine project feasibility.

·         Monitoring of work progress of the Asphalt works and Earth works.

·         Preparation of method statements. Liaising with consultants. Rising inspection request and approval               requests.

·         Take approval of R.F.I from consultants with correct coordination.

·         Understanding in rigid pavement works and asphalt works on all these areas.

·          Preparation of Planning Schedules for Project.

·         Coordination and Monitoring of day-to-day site activities.

·         Preparation of daily progress tracking as per “Look Ahead Schedule”.

·         Updating Baseline and reporting to Client/Consultant and Management.

Experience Hours (Planning & Scheduling): 
0