START Date:
January, 2000
At McNicholas my function as a planner was to be involved with the project from pre –tender stage right through to six monthly / two yearly defect hand over stage.
The biggest and highest valued project was a telecommunications link for a company called Tycom Networks, the project was valued at £300,000,000.00 as it had submarine cables linking it to America, Canada and Norway and my duties included:
•Plan a feasible route from Filey North Yorkshire, down to Cambridgeshire & across to Leeds.
•Walk the routes in their entirety to position splice chambers & pulling boxes.