SIAC Construction (UK) Ltd

Adrian Reddy

First Name: 
Adrian
Last Name: 
Reddy
Professional Since: 
Apr-2006 (19.0 yrs experience)
Oldest experience: 
Mar 2010 (15.1 yrs experience, WARNING: 3.9 years variance with Professional Since)
Years Experience: 
10

Karolina Sucinska

First Name: 
Karolina
Last Name: 
Sucinska
Professional Since: 
Jul-2007 (17.7 yrs experience)
Oldest experience: 
Jul 2007 (17.8 yrs experience, WARNING: 0.0 years variance with Professional Since)
Years Experience: 
3

SIAC Construction (UK) Ltd Civil Engineer

START Date: 
September, 2004
END Date: 
October, 2005
● Scheduling of works;
● Site management;
● Traffic management plans and real life installation;
● Setting out, levelling;
● Site administration;
● Health and Safety on site

SIAC Construction (UK) Ltd Planner

START Date: 
October, 2005
END Date: 
May, 2009
● Establishing construction strategies for projects;
● Scheduling for tenders, ongoing works and Extension of Time & Delay and Disruption Programmes (including resource levels, schedule constraints, risks and opportunities) using Primavera P5 and P6 and MS Project;
● Assisting Project Managers during planning, construction and completion stage of project life;
● Progress Reporting;
● Constant development of schedule layouts to show information requested;
● Continued input into Value Engineering;

SIAC Construction (UK) Ltd Planner

START Date: 
March, 2010
Current Role

SIAC Construction (UK) Ltd Planner

START Date: 
July, 2007
END Date: 
November, 2007
As a section planner of the construction project I was responsible for planning and coordination of the construction works on the Section 4 of M3 Motorway Clonee to North Kells. Using Ms Project to control the progresses of work, and building and controling of the time schedule.Preparing monthly reports, 3 weeks, months looking ahead programmes. Analyzing costs, materials, resources needed for realization of the project.

SIAC Construction (UK) Ltd Lead Planner

START Date: 
November, 2007
As a Project Planner I became responsible for planning and coordination of the construction works on the M3 Motorway for all sections (60 km).Building wide range of Construction Plans, Resource Usage Schedules, Tracking Progresses of The Work, Preparing wide range of Reports, Analyzes. My besic tool is the Ms Project.Duties connected also with Costs Analyzing,Materials Quantities,Resources Allocation. Preparing grafic view of planned works as well as any kind calculations.Possition strictly connected with a Project Management. (Risk Assesment Analyzes, Mile Stones Analyzes, PERT Analyzes)

SIAC Construction (UK) Ltd Planner

START Date: 
March, 2008
Current Role

Darren Beck

First Name: 
Darren
Last Name: 
Beck
Professional Since: 
Jul-2006 (18.7 yrs experience)
Oldest experience: 
Mar 2008 (17.1 yrs experience, WARNING: 1.6 years variance with Professional Since)
Years Experience: 
0

SIAC Construction (UK) Ltd Planner

START Date: 
June, 2006
Current Role