Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Onshore Construction Co. Pvt. Ltd.

vineeth pachidiyan

First Name: 
vineeth
Last Name: 
pachidiyan
Oldest experience: 
Feb 2011 (14.2 yrs experience, WARNING: 41.1 years variance with Professional Since)
Years Experience: 
43

Assistant Planner or Planning Engineer , Onshore Construction Co. Pvt. Ltd., THICKENER

START Date: 
February, 2011

Preparation of types of schedule , budjeting , cost analisation, progress reporting , project monitering , billing

Onshore Construction Co. Pvt. Ltd. Mechanical Engineer

START Date: 
February, 2004
END Date: 
October, 2004
Project: Construction 1260 TPD Air Separation Unit at Ispat industries Ltd. Pen. Raigadh.
Job Responsibilities
Preparation of Fabrication & Erection Schedule for Structure using Primavera.3.1
Preparation of Fabrication & erection schedule according to Structure & Equipment Erection Schedule
Progress Monitoring Planned Vs. actual
Fabrication & Erection of 55 Mtr HT Cold box & Exchanger box structure
Fabrication & Erection of Aluminum, SS, CS & UG Piping
Erection & Alignment of Air Separation Columns, Heat Exchangers - inside Cold box structure