Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Skanska

Jerry Seaborn

First Name: 
Jerry
Last Name: 
Seaborn
Professional Since: 
Jul-2008 (16.0 yrs experience)
Oldest experience: 
Sep 2001 (22.9 yrs experience, WARNING: 6.9 years variance with Professional Since)
Years Experience: 
8

Vamsi Kolliboina

First Name: 
Vamsi
Last Name: 
Kolliboina
Professional Since: 
Oct-1993 (30.7 yrs experience)
Oldest experience: 
Sep 2001 (22.9 yrs experience, WARNING: 7.8 years variance with Professional Since)
Years Experience: 
9

John Jeffree

First Name: 
John
Last Name: 
Jeffree
Professional Since: 
Aug-2004 (19.9 yrs experience)
Oldest experience: 
Mar 2001 (23.3 yrs experience, WARNING: 3.4 years variance with Professional Since)
Years Experience: 
9

Senior Project Planner, Skanska, Bank of China, Brent Civic Centre, London Bridge City, Moorgate Exchange, Olympic Media Centre

START Date: 
November, 2009
END Date: 
November, 2013

Currently working on the various commercial building projects around London

  • London Bridge City - Refurbishment (Asta Powerproject)
  • Bank of China, Cannon Street - Refurbishment (Asta Powerproject)
  • Moorgate Exchange, Telex - New Build (Asta Powerproject)
  • Brent Civic Centre - New Build (Asta Powerproject)
  • Gatwick Airport - Refurbishment (Primavera P6)

Prior to that I worked on the Olympic Media Centre for approximately 2 years (Primavera P6)

Skanska Planner

START Date: 
May, 2010
Current Role

Skanska Planner

START Date: 
May, 2009
END Date: 
January, 2010
● Scheduling for ongoing works (including resource levels, schedule constraints, risks and opportunities) using Primavera P6;
● Quantities management;
● Assisting Project Managers during construction stage of project life;
● Progress Reporting;
● Constant development of schedule layouts to show information requested;
● Continued input into Value Engineering;

Skanska Planner

START Date: 
February, 2010
Current Role

Construction Planner, Skanska, A1 Motoway

START Date: 
March, 2009
END Date: 
September, 2011

A1 Motorway - Poland

Main Duties:Production of detailed construction programme for new build 60km motorway project, monitoring and updating progress, cost & resource monitoring (concrete, aggregate, bituminous) scheduling and re-scheduling, regular reports, Cost Performance Index, S-Curve, Critical Path Analysis, cash flows. Assisting Project Managers during planning and construction stage of project. Development of schedule layouts to show information requested using Primavera P6 software.

Skanska Planner

START Date: 
October, 2009
Current Role

Skanska Senior Planner

START Date: 
July, 2003
END Date: 
July, 2006
• Develop tool install schedule for post passivation/sort conversion utilizing intertool logic & tool frequency rule
• Build resource matrix for five trades from BOQ’s and estimates. Load resource data into P3e/c and update with reconciliation data.
• Create schedule reports and indicators for presentation at weekly coordination and operations meetings.
• Participate in P3 users group meetings. Provide user testing for new application software.
• Develop conversion schedules for existing facilities.