DynCorp International Inc. (US)

Planning Engineer, DynCorp International Inc. (US), Various Projects

START Date: 
November, 2006
END Date: 
November, 2007

Project Handled

 

  • USD 25 Million 500 Man camp at Kabul involving construction of Power / Water Treatment / Waste Water Treatment Plant, Accommodation, MWR, Maintenance & Office Buildings.

Fuad Kurtovic

First Name: 
Fuad
Last Name: 
Kurtovic
Oldest experience: 
May 2008 (17.0 yrs experience, WARNING: 38.3 years variance with Professional Since)
Years Experience: 
4

Sr. Project Controls Specialist / Senior Scheduler - Planner, DynCorp International Inc. (US), LOGCAP IV

START Date: 
October, 2012

September 2012 - present - Project Controls Specialist Sr. (Senior Scheduler/Planner) - Project Controls - DynCorp International, Afghanistan

Al Washington

First Name: 
Al
Last Name: 
Washington
Professional Since: 
Jul-1986 (38.8 yrs experience)
Oldest experience: 
Oct 2006 (18.5 yrs experience, WARNING: 20.3 years variance with Professional Since)
Years Experience: 
42

Construction Project Planner / Senior Planner, DynCorp International Inc. (US), Kennedy Space Center. New Construction. Renovation

START Date: 
October, 2006

Construction Analyst inspect and review constractor's schedules and pay request.  Using MS Project and Primavera schedules.