Project Manager

Project Manager, ACE Winches, Global Portfolio

START Date: 
April, 2014
END Date: 
November, 2015

Manufactured a topside winch and reeler spread with a central PLC control cabin for the Brent Delta decommissioning project - Project Value £1.2Million
 Completed a £4Million manufacturing project utilising a team of engineers, draughting and subcontracted resources for the build which is now being commissioned for a deployment spread to deliver three chain winches used successfully to lay the largest mooring chain in the world.
 Managing hire projects including the first ACE Reel Drive System, up to £1Million
 Leading FAT's for both new build equipment and hire assets

Experience Hours (Planning & Scheduling): 
600
Experience Hours (Cost Management): 
600

Project Manager, Enpro Subsea, Decommissioning

START Date: 
January, 2016

Started Forbes Solutions Ltd, a Project Management and Controls company and have recently completed out first successful project over the last eight months.

Working in a decomissioning project in the North Sea with a suite of bespoke tools it has been very successful.

We are now on the look out for our next project

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
200

Project Manager, Network Rail, (various projects)

START Date: 
October, 2011

5 years Network Rail

Msc Programme and Project Management - Warwick University

APMP

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
150

Project Manager, Network Rail, (various projects)

START Date: 
October, 2011

5 years Network Rail

Msc Programme and Project Management - Warwick University

APMP

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
150

Manager Electrical and Instrument Engineering, Project Manager, PT Vale Indonesia, Tbk, CCP2 FEL3 (Kiln 1, 4 and 5, Coal Mill), CCP2-K2 Execution phase (FEL4)

START Date: 
April, 2012

- Design, review and lead electrical and instrument project.
- Identify development project to improve production and the reliability of production.
- Build and develop strong and high spirit team of engineering
- Manage Capital Project and Operating Project from project initiation, design, construction until handover to sponsor.

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
5000

Lead Cost Engineer, Project Manager, HAM Marine / PMB Bechtel, Ensearch Garden Banks

START Date: 
May, 1994
END Date: 
June, 1995

Responsible for all cost and financial related functions of a Joint Venture Semi Submersible Conversion Project at the HAM Marine Shipyard in Pascagoula, Mississippi, The Enserch Garden Banks Semi Submersible Upgrade and Conversion. Developed tools, established change control, and managed schedules.

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
1800
Experience Hours (Forensic Analysis): 
200

Project Manager, Blue City Company, Blue City Project

START Date: 
December, 2008
END Date: 
September, 2010

Project Manager, Blue City Project

Sawadi, Oman— Dec 2008-Sep 2010

Blue City is a $15 billion megacity project spread over 32 square kilometres and 16 kilometres of coastline along the coastal region at Al Sawaadi. The city will include 20 hotels, hospitals, and university. It will have shopping centres, marina, and schools, golf course, etc. The project manager is responsible for the development of Phase 1 of the project which includes 5-star hotel, residential apartments, golf course and villas.

Project Manager, Multiple, Multiple

START Date: 
September, 1998

IT Consultant: Business Analyst and Project Manager/PMO

  • Italian Airforce
  • Fujitsu Services
  • NATO
  • European Commission 
  • FAO of the UNITED
  • IGT
  • Accenture
  • Business Integration Partners

Project Manager, Construction & Supply for Industry, Sulphuric Acid Fums Extraction System

START Date: 
May, 2001
END Date: 
August, 2001

Responsibilities:

Day to Day site Supervision for site activities with compliance to HSE Policies and Procedures.

Define and acquire all Resources and Materials needed for the Projects.

Provide high level of reporting for a proper completion.

Followed up and coordinated the Schedule, Milestones and Progress.

Project Manager, Conslab Limited, Sunderland 4C Residential Project, Hobsonville.

START Date: 
April, 2016

Responsibilities

Day to Day site Supervision for site activities with compliance to HSE Policies and Procedures.

Define and acquire all Resources and Materials needed for the Projects.

Provide high level of reporting for a proper completion.

Followed up and coordinated the Schedule, Milestones and Progress.