Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Planner

PLANNER, EDWARD AND CHRISTEY, 72 KM OF ROAD CONSTRUCTION

START Date: 
October, 2010
END Date: 
February, 2012

·         Prepare daily, weekly and monthly project reports.

·         Scheduling project using Primavera Project Management.

·         Monitor the actual progress against scheduled program.

·         Preparing look ahead schedules.

Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
800

PLANNER, EDWARD AND CHRISTEY, 72 KM OF ROAD CONSTRUCTION

START Date: 
October, 2010
END Date: 
February, 2012

·         Prepare daily, weekly and monthly project reports.

·         Scheduling project using Primavera Project Management.

·         Monitor the actual progress against scheduled program.

·         Preparing look ahead schedules.

Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
800

PLANNER, EDWARD AND CHRISTEY, 72 KM OF ROAD CONSTRUCTION

START Date: 
October, 2010
END Date: 
February, 2012

·         Prepare daily, weekly and monthly project reports.

·         Scheduling project using Primavera Project Management.

·         Monitor the actual progress against scheduled program.

·         Preparing look ahead schedules.

Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
800

Engineer, Planner, Ontario Hydro, Reactor Retubing Project

START Date: 
June, 1982
END Date: 
June, 1990

Technical Unit Sytem Engineer - Development of Work Plans and Schedule logic

Large Scale Fuel Channel Replacement Project - Development of Work Plans and Logic, Tooling development and training

Recommissioning Engineer - Return to service scheduling activities

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
500

Planner, Northumbrian Water Ltd, Northumbrian Water Projects

START Date: 
June, 1990
END Date: 
June, 1995

Design and costing of water mains extensions and diversions, ordering non-stock material, control of costs, monitoring progress of schemes, preparation of final accounts and dealing with prospective developers and site agents on a day-to-day basis

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000

Planner, Balfour Beatty, EAST LONDON LINE - VALUE: 450m GBP

START Date: 
June, 2007
END Date: 
December, 2009

Design Planner - Planning, co-ordinating and prioritising design packages 

Construction Planner - Civils and Infrastructure - Providing planning support for Three Bridge Replacements, Four Station Escape Stairs, One Rail Junction and Two Major Pipe Protection Structures

Comms Engineer

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Forensic Analysis): 
400

Planner, Bond Interiors, Gucci shop

START Date: 
February, 2014
END Date: 
February, 2016

I have 3 Years Experience In Aluminum Industries I have Spend 3 years wit Facade Industries 

Experience Hours (Planning & Scheduling): 
900

Planner, Ramboll UK Ltd, (Various projects) UK & Overseas

START Date: 
June, 2015

Planner on Building, Civil, Highway & Infrastructure Projects - Design & Construction Phase

Planner, Ramboll UK Ltd, (Various projects) UK & Overseas

START Date: 
June, 2015

Planner on Building, Civil, Highway & Infrastructure Projects - Design & Construction Phase

Planner, CBC Limited, Various Projects up to £10m

START Date: 
May, 2015

update update update update update update update update update update

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Forensic Analysis): 
150