Planner

Planner, Phillips 66, AMEC, Tank maintenance / New build

START Date: 
August, 2012

Single Planner for a 15 Million pounds per year storage tank project at Phillips 66 Humber refinery seconded directly for the Client.

(New tank build, major tank repair and tank maintenance). 

Heavily involved with both client and contractors planning, scheduling and reporting multi-phase, multi-discipline and fully resourced P6 programs. Creating outputs for project management, business production, engineering, commercial, and coordination teams.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500

Planner, FLSMIDTH PRIVATE LTD, EPC

START Date: 
January, 2011
END Date: 
July, 2014

Working as a planner in a private concern for the last 4 year.

Preparting the initial plan for procurement activities using primavera

Following up each activity as per schedule.

Monitoring and controlling the activities using primavera.

Planner, Thames Water, Thames Tideway

START Date: 
April, 2013
END Date: 
September, 2013
• Ensure that programmes are updated and monitored against agreed contractor schedules • Review the Contractor’s P6 programme regularly, providing information to the management team in order to control resources, programmes, projects and contractors performance
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000

Planner, Subsea7, OFFSHORE PROJECTS

START Date: 
September, 2013
• Scenario planning and optimisation of programme, outputs, risk and opportunities • Responsible for the production of the overall Global vessel schedule, supporting the requirements of Commercial, Project and Operations and Offshore Resource functions. • Regularly reviewing and verify the quality of inputs from prospects/tenders/firm work by country planners

Planner , Balfour and Beatty , Various @ London

START Date: 
June, 2011
Planning tender programme, construction programmes and control projects- Substructure, superstructural and fit-out works

Planner, Bina Schedulers Sdn Bhd, Kelana Jaya LRT Extension Project

START Date: 
March, 2013
END Date: 
May, 2013
  • Project Planning and Scheduling for Linear Project.
  • Project Progress Reporting.
  • Delay analysis for Extension of Time application.
Experience Hours (Planning & Scheduling): 
500

Planner, NJS Consultants, Al Amerat Waste Water Project

START Date: 
September, 2003

 

SIVASANKARI

 

Email ID:  sivasankarisundar@gmail.com      Mobile: +968 -92615196

 

 

SUMMARY

Experience Hours (Planning & Scheduling): 
15000

PLANNER, "Gannett Fleming, Inc", ASHGAL PROJECTS

START Date: 
January, 2014

A PLANNER & SCHEDULER FOR A COMPANY IN  QATAR RESPONSIBLE FOR BASELINE PROGRAMME SCHEDULE,WEEKLY AND MONTHLY REPOR,TRACKING PROGRESS AND ALSO PROJECT MANAGMENT ADVISER. 

Experience Hours (Planning & Scheduling): 
13000
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
3000

Planner, Alcon Nigeria Limited, Fabrication of Mechanical & Structural Equipment for Oil & Gas

START Date: 
February, 2014

As a Planner in Alcon Nigeria Limited Structural Fabrication & Precast Yard since February 2014, i Schedule, Cost Project & Undertake Daily Progress Measurement. I also ensure that Resources allocated to activities are Effeciently Allocated. And each Individual Project Finishes as at when Scheduled.

Planner, Alcon Nigeria Limited, Fabrication of Mechanical & Structural Equipment for Oil & Gas

START Date: 
February, 2014

As a Planner in Alcon Nigeria Limited Structural Fabrication & Precast Yard since February 2014, i Schedule, Cost Project & Undertake Daily Progress Measurement. I also ensure that Resources allocated to activities are Effeciently Allocated. And each Individual Project Finishes as at when Scheduled.