Design / Construction - Planning Engineer

Design / Construction - Planning Engineer, Consortium formed by: Koch, Bentro Pedroso, CME and KBB, Carriço Gas Storage

START Date: 
July, 2000
END Date: 
July, 2002

Planning Engineer

Establish master and detailed scheduling for consortium.

Progress measurement, partners and client liase, internal and external reporting, progress curves, simulation of scenarios

Design / Construction - Planning Engineer, Bureau Veritas, Almaty Financial District Project - Turan Alem Phase

START Date: 
November, 2007
END Date: 
May, 2009

Project 1:
Almaty Financial District – Phase 2 – Turan Alem Bank Project (Almaty, Client: Capital Partners, Bank Turan Alem, Belgravia) (BOMA Gross area 160.000 sqm)

Responsibilities as Planning Engineer (Reporting to Construction Technical Manager)
•     Preparing of Design Schedules, Tender Schedules, Permit Schedules,
•     Reviewing the method statements for the scheduling,
•     Preparing of level 2 Construction Schedules,
•     Controlling and approval of Contracto