Whessoe International (Projects)

In Kingdom Project Manager / Construction Manager, Whessoe International (Projects), Rabigh Refinery Project

START Date: 
July, 2006
END Date: 
October, 2007

Construction Manger responsible for the build of 4 Cryotanks, 28 ambient tanks, 6 spheres and the associated plant and pipework.

Project Construction Coordinator / Outage Manager, Whessoe International (Projects), Isle of Grain Expansion Project (LNG)

START Date: 
March, 2003
END Date: 
December, 2004

Project Planning Manager on the Isle of Grain LNG Import Facility and Management of the associates ti-ins/outages with the existing plant