Area Planning Engineer, PetroSA (PTY) Ltd, Refinery Shutdown

START Date: 
November, 2009
END Date: 
December, 2014
  • Shutdown And Turnaround Planning And Execution (Implementing 7 Phases Planning Cycle).

 

  • Compilation of Shutdown and Turnaround Schedules (Bar Charts Using Primavera And Or Ms Projects.

 

  • Originate And Review Planning And Scheduling Documentation.

 

  • Facilitation the Execution of Shutdown and Turnaround Plans and Schedules.
  • Reporting and Continuous Improvement of Maintenance Kpi’s.

 

  • Provide Guidance To Formulation Of Long Term Outage Plan.

 

Experience Hours (Planning & Scheduling): 
10400
Experience Hours (Cost Management): 
1400

Stanley Fillis

First Name: 
Stanley
Last Name: 
Fillis
Professional Since: 
Nov-1994 (30.1 yrs experience)
Oldest experience: 
Feb 1995 (29.9 yrs experience, WARNING: 0.2 years variance with Professional Since)
Years Experience: 
15

PetroSA (PTY) Ltd Planner

START Date: 
April, 1990
END Date: 
September, 2002
Position: Mechanical Foreman & Planner
Responsibilities: Routine Maintenance, Turnarounds and Shutdowns including planning and execution in GTL Refinery

PetroSA (PTY) Ltd Senior Planner

START Date: 
May, 1998
Natural Gas Offshore Projects Planning / Scheduling. Onshore GTL [Gas to Liquids]Refinery Projects, Shutdown, Turnaround & Maintenance Planning. Natural Gas Facility [FA Platform] Offshore startup & commissioning planning. Cost Controlling. MS Project software. Primavera P6 Project Management scheduling software. MS Office. SAP Enterprise software experience link to Primavera / Inspire interface. Certified Mechanical & Piping draughtsman. Qualified Mechanical Tradesman.