The Greater Gorgon Area is located 200km offshore of the northwest coast of Western Australia and contains in excess of 40 trillion cubic feet of recoverable natural gas.
· 16.5m Manhours (EPC)
· 200K Tonnes overall
· 97K Tonnes of structure steel
· 97,000 Pipe Spools
· 1.5m meters cable
· 51 Module
- Schedule analysis including development of 8 week lookahead schedules. Creating What if scenarios based on current fabrication status, structural and piping, predicting on site start date.
- Liaise between Sub-Contract planning team regarding claimed progress and slippage.
- Analysis of shop fabrication data, both piping and structural. Providing superintendents reports per shipment and module.
- Yard progress verification: analysis of Sub-Contract claimed progress against company verified progress.