Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Usage and Shift Patterns

5 replies [Last post]
Luke Meagher
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 1 Nov 2012
Posts: 5
Groups: None

All,

Is it possible to apply shift patterns to a resource?

You can apply a calendar to a particular resource, for any given activity, but is there the ability to then also apply a shift.

We are using 24 hour working calendars along with Shift calendars and I wondered if you could assign both to a resource in a given activity.

Regards

Replies

ali Khosravi
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 27 Dec 2007
Posts: 3

Hi 

I am using MSP 2013 and I for each job i have a different supervisor - updated in text1. now i need to know in my shut schedule, during the execution, the break down of resource assignments for each supervisor. in other words i need to group resource assignments per each supervisor. 

pitty is resource assignment does not let filtering / grouping on task fields and when i use task assignments to filter for resource names, i its completely meaningless as it creates a group for each resource allocation combilation ... ie. groups for "FT", another for "FT[2],TA".

am i missing anything here? some help would be appreciated.

 

Regards,

AK

Luke Meagher
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 1 Nov 2012
Posts: 5
Groups: None

All,

I am currently using Primavera P6 v7 Service Pack 3.

Thanks,

Luke

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Another use of shifts is when the whole crew changes depending on the season.

It is not uncommon for equipment used during winter be different to equipment used during the summer for the same activity, by the same token not only the equipment changes but the whole crew productivity.  

Better schedule models will automatically select the right crew when the activity switches from one season to another and will adjust activity duration according to differences in productivity.

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Shift Work is not difficult, only you need to know are:

  1. the rules of assignment, and 
  2. software capable of modeling the rules.

I use Spider Project a software that is capable of both.

We use the concept of Teams for when resources must work together, for meeting resources. If resources can work independently of one another just make them members of a single resource team. In this way on a single activity you can model as many different teams you need.

You assign a calendar to the activity that will include all work time for which resources are allowed to work, usually a 24/7 calendar will do it unless there are certain hours the resources might be available but you do not want them to work on the activity. Say a resource is available on a second shift seven days a week but it is a requirement that on Mondays no work is allowed on second shift. Therefore the activity calendar will exclude second shift on Monday and the resource will be available to do work at another activity on Mondays.

The following example is the minimum expression of such scenario that many so called advanced software cannot tackle. Please don't take it for granted what I say, try it by yourself. 

  • One activity Scenario
Activity 1 = 500 cm rock excavation - Resource 1 production 10 cm/hr and works Monday, Tuesday and Wednesday 10 hrs/day - Resource 2 production 15 cm/hour and works on Wednesday, Thursday and Friday 10 hrs/day 
  • If activity starts on Monday:
Monday =>> Resource 1 will produce 100 cm, Tuesday =>> Resource 1 will produce 100 cm, Wednesday =>> Resource 1 will produce 100 cm, Wednesday =>> Resource 2 will produce 150 cm, Thursday =>> Resource 2 will produce 50 cm in about 3 hours, Activity will take 3 days 3 hours. 
  • If activity starts on Wednesday :
Wednesday =>> Resource 1 will produce 100 cm, Wednesday =>> Resource 2 will produce 150 cm, Thursday =>> Resource 2 will produce 150 cm, Friday =>> Resource 2 will produce 100 cm in about 7 hours, Activity will take 2 days 7 hours. 
  • If your software is not capable of modeling the above, simple shift work on a single activity, then you are using the wrong tool. Every time the activity is delayed, the distribution of work is shifted, when you have many such activities and work on different hour shifts, different days it can become quite complicated. For a single shot you can use incapable software with manual distribution of work among shifts for anything else distributing work by hand is nuts.
Of course this is just an illustration, you shall be able to model more complex real life scenarios, like multiple teams working on the same activity on different shift.  Please expose in more detail what you want to model, shift work is easy if you have the right tool. The problem must be solved within the ways of each particular software, that is if the software is capable. 
Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

It would help if you could tell us what software you are using?