Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Filters in Primavera Risk Analysis

4 replies [Last post]
UK Planning Engineer
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 19 Jul 2012
Posts: 15
Groups: None

Is there a way to filter the activities in Primavera Risk Analysis similar to how you would in P6?

I'm trying to filter activities with no predecessor/successor from a dodgy schedule ready for analysis I received but there doesn't seem to be a suitable field in the drop down filter list and this should be the simplest filter to switch on?!?

Surely it can't just be going back and forth from the schedule check to correct all the errors as this seems to be very clunky? But the filter list in PRA doesn't even seem to have the basics?!?

Are there also any other common filters that anyone uses as I'm having a great deal of difficulty in setting them up on PRA?!?

 

Thanks everyone!

Replies

Santosh Bhat
User offline. Last seen 1 day 20 hours ago. Offline
Joined: 15 Apr 2005
Posts: 381

Firstly, PRA is OLD, you should seriosuly look into some of the newer SRA tools out there.

 

But one workaround to your dilema - Filters are only applied to tasks, not to links. Show the "Preceding Tasks" and Suceeding Tasks" Columns. Remove any Grouping/organisation and then sort by each of the columns to see which tasks are null in each column.

 

Rafael Davila
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

If there is no such pre-defined filter in your software then with the use of UDF (User Defined Field) a few formulas, a few simple filters and a script to automate execution you should be able to create the filter.

In the following video you will see the use of a pre-defined filter as well as the use of a script.  After the script is defined all it requires is to run it with a few mouse clicks, easier and faster than using Excel.

Pre-defined dangling logic filters are a better option anyone can use.

Predefined_Filters

Good Luck

Rafael Davila
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

When creating your filters please be reminded that it is possible for activities to have both predecessors and successors yet still suffer from dangling – hence inadequate – schedule logic. These cases – generally categorized as dangling finish and dangling start – are also known as “orphan relationships.”

Dangling01


Dangling02
 

In such case it is possible the schedule reports miss to highlight the dangling finish/start.