Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

PRA Cost Roll Up

No replies
Simon Martin
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 29 Jan 2008
Posts: 13
Groups: None

Hi,

In the Risk Outputs tab of PRA, the P50 cost does not seem to roll up properly. For example the sum of the P50 costs of activities do not always equal the P50 cost of their WBS element, and the sum of the P50 costs of WBS elements does not always equal the P50 cost of their parent WBS element. 

Has anyone else had this issue? 

Any assistance would be greatly appreciated.

Kind regards,

Simon