PRA 8.6: Why do Oppty Hammocks cause zero TF?

No replies
kevin herring
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 18 May 2010
Posts: 5

 

Background:  PRA V8.7, using opportunities within the risk register of PRA

My PM wants an explaination why an activity (that contains an oppty node) with 1.5yrs probilistic float has a
100% critical index. From what I can see it is the hammock off the Oppty node
with zero total float causing it.

Is there a valid reason why this happens?

Thanks in advance,

Kevin