Hi All.
I am Really happy to be with you here on Planning Planet.I am finding it very helpful indeed.Thaks to all of you for contributing and sharing the knowledge.
My Questions are about Primavera Risk Analysis.
Q#1. I need to know the Basis that how the Risk Impact (Low,Medium,High,Very High etc.) . For example if you have a project of say,12 Months, and a Risk is Impacting the Project by say,1 month, then how it is evaluated that this risk belongs to,low,Medium,High or very High Impact category??
Q#2. How should I give accurate values in the Impact Ranges ( i.e Very high (Schedule) = 20 to 40 days or Cost Very High (2000 USD to 3000USD etc.)
i need a guidline from those who are experienced amongst you because i am still junior in this field and need a helping hand.
I have googled this topic for many days and when i failed to reach any solid decision then i have posted this query here on this forum.
Mny thanks to all in advance.
Happy planning.
Replies