Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Typical planning spec.

4 replies [Last post]
Frank Neal
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 3 Feb 2003
Posts: 44
Groups: None
What is the ideal number of tasks a project should be broken down?

when writing a requirements specification for an RFP.

I have heard 14 max duration and 20 max duration. as typical

Is there an industry standard say for typical large Building type projects?, residential, mixed use, commercial.

Replies

Samer Zawaydeh
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Hi,

As Rodel said, the PMI and the AACEI both recommends that the max activity duration be 2-3 times the reporting cycle durtation.

With kind regards,

Samer
Daniel Limson
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None
Hi Frank,

How are you? Where are you based now?

Regarding your question, I have always advocate to keep a programme "simple and manageable" The level of detail should be kept to a minimum and 2 weeks is I think reasonable. I beleived that the guys doing the work in the field should be given big targets and a chance to plan their work in detail, afterall, they know better than us on how to accomplish the work in the field, in the best and shortest possible way. They should not be dictated nor micro-manage to a certain extent and I believe this makes them more productive.

I am currently in Hongkong. You can email me at limsondm@yahoo.com

Best regards,

Daniel Limson
Rodel Marasigan
User offline. Last seen 25 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Frank,
Reference: "PMI Project Scheduling Standard" – durations should be at least 2 times less than the update cycle and never more than 3 times of the update cycles with the general exceptions of continuous activities.

Some planning best practice book says – minimum of 1 day cycles so it is easier to track and maximum of 2 weeks depends on the size of the projects.
Frank Neal
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 3 Feb 2003
Posts: 44
Groups: None
my question should read max duration of a task, 14d or 20d except for say long lead items,