Quick Risk Template - distributions

3 replies [Last post]
Dennis Hanks
User offline. Last seen 8 years 45 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310
Is there any way to change the default distribution in the quick risk template for Pertmaster 8.53?

Current default distributions are BetaPert, Enhanced, Triangle, and Uniform. I would like to add Trigen and make it the default.

Software no longer maintained by client, so stuck at 8.53 and no longer have access to Primavera support.

Any thoughts appreciated. Thanks.

Replies

Sudheerkumar Gurram
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 16 May 2005
Posts: 10
Dennis Hanks
User offline. Last seen 8 years 45 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310
Thanks Andrew;

This is what I currently do - part of my standard view. I was hoping to eliminate the fill down step by making the default change in Quick Risk.
Andrew Podolny
User offline. Last seen 1 year 32 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Hi Dennis.
There is workaround - add 2 columns into your Risk View:
1st from Risk Inputs group - Duration Distribution
2nd from Risk Inputs group - Use Duration Distribution

Assign the Trigen distribution to the topmost activity through the bottom panel - you’ll see the changes in the recently added columns. Use ’Fill Down’ feature to fill these 2 columns.

Regards,
Andrew