Hello,
Im using Pertmaster project risk 8.5.
Im preparing a schedule,and using Demote to group the activities, and then I used Organize function to group the schedule by a task user field.
after that I re-organize the schedule to the original summary structure, then i add some more activities and summary activity (by demote).Up to now every thing is OK.
Now the problem is when I try to re-organize the schedule to the original summary structure, the change i made to the summary structure before all lost.
to make it clear, the problem is the organize function (with option "original summary structure")will restore the summary structure to before the first time you run organize. or to say when you used Organize function, you will have no change to edit the original summary structure.
Does anyone know how to solve the problem?
thanks,