Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Help! Pertmaster Project risk - Organize Problem

1 reply [Last post]
Zhang Haixiang
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
Hello,

I’m using Pertmaster project risk 8.5.
I’m preparing a schedule,and using Demote to group the activities, and then I used Organize function to group the schedule by a task user field.

after that I re-organize the schedule to the original summary structure, then i add some more activities and summary activity (by demote).Up to now every thing is OK.

Now the problem is when I try to re-organize the schedule to the original summary structure, the change i made to the summary structure before all lost.

to make it clear, the problem is the organize function (with option "original summary structure")will restore the summary structure to before the first time you run organize. or to say when you used Organize function, you will have no change to edit the original summary structure.

Does anyone know how to solve the problem?

thanks,

Replies

Dave Jones
User offline. Last seen 11 years 20 weeks ago. Offline
Joined: 4 Sep 2009
Posts: 11
Groups: None
Have you checked the bug fix list for version 8.6?