I believe that the up dated programme is the monitoring of the proress for all the base-line programmes activities at certain data date based on the actual start and finish dates and the %completed for each activity so, it can show the recent status of the complete project .
The following up proramme can be used only to monitor specific nos. of activities for certain peroid and we can get the status of those activites during that period and we can use the same to prepae weekly following up programme or two weeks ahead following up programme for the main activities.
"Follow-up Schedule" usually refers to a schedule that is developed and implemented to follow after the completion of the main Project Schedule.
An example would be in Engineering Design, following the completion of the work, a "Follow-up Schedule" is often implemented.
The type of work covered:
- Provide technical support during Construction /Comm.
- Maintain / update design,
- Resolving site technical querries
- Finalise Vendor information
- Dealing with authorities / other parties etc.
The schedule results in creating a need for a group of technical resources to support the Project post completion of the design.
As for an "Update Schedule", never heard that one before, as a quess it could be a schedule that has been updated with the current progresss and status.
If you check the following site their is an interesting list of standard terms (Glossary section), mind no referance to your two terms.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Mounir,that means you have agreed with me,thanks
i think that:
Update Schedule: means to get the actual dates and the % complete for the activities.
Follow-up Schedule: means to monitor specific activities or the whole schedule (eg.like a 4 weeks look ahead).
Hi,
I believe that the up dated programme is the monitoring of the proress for all the base-line programmes activities at certain data date based on the actual start and finish dates and the %completed for each activity so, it can show the recent status of the complete project .
The following up proramme can be used only to monitor specific nos. of activities for certain peroid and we can get the status of those activites during that period and we can use the same to prepae weekly following up programme or two weeks ahead following up programme for the main activities.
Hi
"Follow-up Schedule" usually refers to a schedule that is developed and implemented to follow after the completion of the main Project Schedule.
An example would be in Engineering Design, following the completion of the work, a "Follow-up Schedule" is often implemented.
The type of work covered:
- Provide technical support during Construction /Comm.
- Maintain / update design,
- Resolving site technical querries
- Finalise Vendor information
- Dealing with authorities / other parties etc.
The schedule results in creating a need for a group of technical resources to support the Project post completion of the design.
As for an "Update Schedule", never heard that one before, as a quess it could be a schedule that has been updated with the current progresss and status.
If you check the following site their is an interesting list of standard terms (Glossary section), mind no referance to your two terms.
www.planningengineers.org
Regards
John