Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Effective steps to manage large-scale changes in an ongoing project without derailing it

3 replies [Last post]
Mahendra Gupta
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 25 Feb 2020
Posts: 14
Groups: None

I have observed that many new project managers fail to handle scope change, leading to the project's halt or failure. Is there any way possible to manage significant change requests by clients effectively without hampering the project?

Replies

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5240

Keep It Simple, do not leave rookies alone until they get proficient at change management; this should prevent failure to handle change management unless the problem is on the other side. 

An experienced Project Manager should be proficient at estimating and scheduling, until rookies become proficient the estimator and scheduler should assist them. Needless to say top management should always look at what is going on, a look at the change management logs will let them know when the problem is getting out of hand for them to get more involved.

The Contract Change Control Process is usually defined by the contract, may not be easy to change, probably you will have to live with it for the whole contract duration. Of course you can give it a try. 

If the problem is on the other side when there are too many changes your best option may be to abandon the Construction Project.

Too Many Change Orders May Provide Basis For Abandoning Construction Contract | Last & Faoro Attorneys At Law

Patrick Weaver
User offline. Last seen 1 day 21 hours ago. Offline
Joined: 18 Jan 2001
Posts: 382
Groups: None

You need to set up an agreed change control process with the client to minimize processing time and resolve disagreements quickly (even if the resolution is 'we will work on this basis and fight about the difference later').  The key steps are:

1. Agreeing there is a variation (many changes precede the issue of a change order)

2. Scoping and costing the change

3. Agreeing the effect and cost

4. Updating the project control documents (schedule cost plan, etc.) 

These steps need resources to implement - understaffing simply creates bigger issues. 

Agreeing the change usually needs management involvement - setting up a Change Control Board or independent assessment process will facilitate agreement, and agreement to disagree.  

Some more ideas are at: https://mosaicprojects.com.au/PMKI-SCH.php

Zoltan Palffy
User offline. Last seen 3 days 1 hour ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

change orders always add 2 things manhours and dollars. SO it is necessary to capture the additional scope as task in the schedule to see if there is a distuption to the schedule and if that effects the manpower and projected cash flow.