Can software solve the issues on time tracking and billing for projects ?

2 replies [Last post]
nikhil joseph
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 25 Jan 2016
Posts: 17
Groups: None

Many say that software can solve and manage all your projects. Does installing a software gives solution to time tracking , scheduling and billing. Kindly give comments. 

Replies

Rafael Davila
User offline. Last seen 2 weeks 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

To pretend that one size fits all is wrong, I can envision that in many industries the integration is feasible and desirable.

In construction jobs the use of Critical Path Scheduling software for billing it can be problematic when you are not allowed to finish an activity because some pay element is not finished while all successor can start creating a distorted schedule that will require a fix for every such occurrence.

The danger of allowing cost reporting to overshadow and to distort accurate schedule reporting is that the myriad functionality of and purposes for the schedule database are invalidated by distorted and inaccurate schedule information.

  • http://www.nflaace.org/index_files/john_orr_cost_loaded_schedule_updating_pdf.pdf

The above reference illustrates the issue but the proposed solution can be short of being good enough as the proposed fix in logic will again generate an out-of-sequence event every time a pay item within the activity starts before a predecessor of this activity finishes. In many cases the fixed logic will require an independent fix as it happens in many out-of-sequence events where no single fix is going to solve them all.

As if not enough the situation becomes intolerable when the contract requires that every change in logic as well as to the payment schedule to be submitted for approval. 

  • http://www.planningplanet.com/forums/guild-project-controls-gpc/591073/09-managing-project-progress 
Harry vent
User offline. Last seen 7 years 33 weeks ago. Offline
Joined: 16 Jun 2016
Posts: 6
Groups: None

Yeah, software assist to manage all our business process in a single platform. We use Apptivo software to manage projects, customers, keep track & scheduling and generate invoice based on services. It's cheap comparing to another apps in market place, easy to access by newbie.