Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Time Is a Cost Even When Nobody Says How Much

2 replies [Last post]
Stephen Devaux
User offline. Last seen 1 week 6 days ago. Offline
Joined: 23 Mar 2005
Posts: 668

I just published a new blog post “Time Is a Cost Even When Nobody Says How Much” at the Total Project Control  website.  The new blog explains to that even when the sponsor/customer doesn’t recognize the value/cost of time and/or doesn’t know how to incorporate it in a contract or charter, this information is still of particular value to the project manager. It shows how she should go about raising the issue with the sponsor/customer and how she can add clearly quantified value to the customer, the team and herself by restructuring the charter or contract to incentivize what the sponsor/customer wants: a more valuable project through earlier delivery.

Fraternally in project management,

Steve the Bajan

Replies

Stephen Devaux
User offline. Last seen 1 week 6 days ago. Offline
Joined: 23 Mar 2005
Posts: 668

Huh! Thanks, Mike.

Dunno what happened. This will work.

Fraternally in project management,

Steve the Bajan

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Steve

Web link seems to be wrong.

Best regards

Mike T.