Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Lump sum/ Remeasurement

2 replies [Last post]
ronron martinez
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Hi, Expert

We have new project going to carry out, I've go thru the contract and it was mention that the claim is base from remeasurement.

To clarify what does remeasument means and how to substatiate the claim in what basis of the remeasurement?

 

Regards

Ron

Replies

Omer Osman
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 28 Feb 2011
Posts: 7

Hi Ron,

As Mike says, it is all about paying according to actual quantities, as in many cases the actual vary from the estimated as in the BOQ plus or minus, and the difference is settleed by negative or positive change order.

 

BR

Omer

Mike Testro
User offline. Last seen 27 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ron

Remeasurement is where the quantities of the work at tender stage are deemede approximate and the actual volumes will be measured and paid as the work proceeds.

This is normally done by a qualified QS who will use the specified method of measurement.

Regarding the programme there is usually a clause that states the % increase or decrease that has to be absorbed before the programme can be adjusted.

In normal circumstances a change in quantities is not a variation.

Best regards

Mike Testro