Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

NEC Vs FIDIC

5 replies [Last post]
Sankar Vijayan
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 21 Sep 2010
Posts: 58
Groups: None

 

Dear All

Can any one Descripe & differentiate between FIDIC & NEC? I want to prepare a PPT for this

 

thanks & regards

Sankar Vijayan

Replies

Mike Testro
User offline. Last seen 36 weeks 4 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sankar

They both have different forms for diffedrent types of contract ie EPC, Employers Design. Fixed price, Remeasure BOQ etc plus a section for Sub-Contracts and Engineering / supervision etc.

Best regards

Mike Testro

Sankar Vijayan
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 21 Sep 2010
Posts: 58
Groups: None

dear sir,

Can u elaborate the point

2.  To present multi use suites of forms for most procurement / construction processes.

Thanks

Sankar

Mike Testro
User offline. Last seen 36 weeks 4 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sankar

I would suggest NEC is more suitable PROVIDED both the Employer and the Contractor are willing to deploy the people required to administer the contract correctly. Each will need at least one full time planner on the project.

NEC is worse than useless if it is not operated correctly.

Best regards

Mike Testro

Sankar Vijayan
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 21 Sep 2010
Posts: 58
Groups: None

Dear Sir,

Thanking you for your valuable reply .I am now working with  an EPC Contractor .We are now focusing on Buildings(Residentials) & Factories.Early for construction of an  airport we followed NEC.but for Residential buildings which is better in contractor's point of view FIDIC or NEC?

Mike Testro
User offline. Last seen 36 weeks 4 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sankar

Rather than the differences here are some of the similarities in that they both set out:

1.  To be risk neutral.

2.  To present multi use suites of forms for most procurement / construction processes.

3.  Have an independent CA / Engineer administer the contract.

Some differences are:

NEC sets out to manage time issues pro-actively.

FIDIC relies on contractor's entitlement following relevant events.

NEC has the programme at the centre of the contract administration.

FIDIC uses the programme as a non contract document.

Best regards

Mike Testro