Dear All,
In my project, there is a contravercy, that
This project is being handed over to us by part by part with delay by other parties/contractor. The project completion time as per contract was completed (one year before) and not yet handed over completely and works by other parties and contractor is going on.
The Project management consultant, who is a owner's representative did not provide any time extention as well as there is no proper handing over dates at present available. PM consultant did not approve any schedule and every time new milestone without handing over dates.
1. They (PM consultant) started the penality against us and keep on deducting month by month. But they are not willing to pay full preliminaries (i.e Overhead Amount) even the contract period was over.
2. What is the procdure to claim the full and more preliminarie
3. What is the procedure to inform the failure of project management consultant to claim with Owner/arbitration.
Please give your valuable suggestion/provision/reference
Replies