Primavera P6 - Version 8.1 - Calendar Assignment Issue

5 replies [Last post]
Mahavir Bhatt
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 3 Mar 2013
Posts: 4
Groups: None

Good Day All,

In Primavera P6 Version 8.1 I have developed a construction calendar that uses 10 hours work shifts. When I allocate this calendar to an activity with original duration of 5 days it changes the finish date of this activity to show completion of this activity on 4th day and not the 5th day as should be the case. Does anyone know the reason why Primavera computes the finish date that is ending at the end of 4th day but not the 5th? I am in a rush to complete my baseline so any help in solving this riddle is highly appreciated. My email address is: CostControl@live.com.

Thanks in advance for your time and efforts.

Mahavir Bhatt

Replies

Mahavir Bhatt
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 3 Mar 2013
Posts: 4
Groups: None

Thank you Abilash, & Raymund,

I have found the answer to this puzzle. The trick lies in customizing the Time Period to match with the Hours / Work Shift. Thanks again for your help. Regards, Mahavir

Mahavir Bhatt
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 3 Mar 2013
Posts: 4
Groups: None

Thank you Abilash, & Raymund,

I have found the answer to this puzzle. The trick lies in customizing the Time Period to match with the Hours / Work Shift. Thanks again for your help. Regards, Mahavir

Abilash Palakkada...
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Pls check your clander assigment with activity and resource
Abilash Palakkada...
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Pls check your clander assigment with activity and resource
Raymund de Laza
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Check your Time Period.