Maybe P6 is not using the original old values from P3 but is simply making the calculation of quantities and arrving to the same value as P3 (how would P6 import a value that was not available anymore for importing ?).
Check your calendars, resources, units, unit/rate and the explanation is in one or several of these values not matching the imported database
BR
JMFrade
Member for
16 years 8 months
Member for16 years8 months
Submitted by Ariel Malibiran on Sat, 2012-11-24 11:04
Also, I noticed that the budgeted quantities have been changed (ie, increased by 8 times the BQ in P3) this is maybe because in P6, 8hrs per days is specified in the User Preferences, Time Units. I'm not certain about this.
The odd and big question is, how is that possible that p6 used the original cost considering that i have already changed the cost using the global change.
Member for
15 years 11 monthsYou changed the Cost Manually
You changed the Cost Manually in P3 but the Reosurce Price per Unit is carried with the Resource when exported.
When Importing, P6 will calculate as Resource Unit x Resource Unit price = Budget Cost.
Member for
20 years 4 monthsAriel. Maybe P6 is not using
Ariel.
Maybe P6 is not using the original old values from P3 but is simply making the calculation of quantities and arrving to the same value as P3 (how would P6 import a value that was not available anymore for importing ?).
Check your calendars, resources, units, unit/rate and the explanation is in one or several of these values not matching the imported database
BR
JMFrade
Member for
16 years 8 monthsAlso, I noticed that the
Also, I noticed that the budgeted quantities have been changed (ie, increased by 8 times the BQ in P3) this is maybe because in P6, 8hrs per days is specified in the User Preferences, Time Units. I'm not certain about this.
The odd and big question is, how is that possible that p6 used the original cost considering that i have already changed the cost using the global change.
Any idea please!
Regards,
Ariel