Hello,
I have an activity which are currently statused as not started and is sitting on the data date. The activity has 100 Budeted Labor Units.
It turns out that this activity was actually completed a while ago, so I 'retrospectively' assign the actual start/finish dates, and the activity moves back to when it actually occurred.
However, now when I run a 'Cumulative Budgeted Labor Units', it still shows these units as being 'earned' in front of the status date.
To fix this, I have worked out that I need to change the status date back to before the activity actually started, then un-start the activity, then reassign the actual start/finish dates, then move the status date back to where it is supposed to be.
If I have many activities like this, then it is a very time consuming process.
Can anyone suggest a faster way of doing this? I was hoping to find date fields called 'Budgeted Units Start/Finish' that I could manually change, to correct this problem, but there doens't appear to be anything like that.
I can appreciate why this behaviour exists (to maintain consistent earned units values after each update), but for now i'd like to override this behaviour.
Thanks, Hugh.
Replies