Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Summary Task % Complete

No replies
mukunda y
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

I applied dummy resource & unit cost, it is giving schedule % complete & actual % complete in the summary task  , i tried to find out the basis of this summary task % complete, coulld not find the base, Please advise me experts....what is the formula behind this,,, ,...

 

Mukunda