critical path and loop

1 reply [Last post]
moh ham
User offline. Last seen 9 years 45 weeks ago. Offline
Joined: 3 Mar 2011
Posts: 8
Groups: None

Hi,

I'm beginner in primavera; I just want to know how can I discover if there is any loop on the Critical path

 

Thank you

Replies

Gary Whitehead
User offline. Last seen 6 years 6 weeks ago. Offline

Primavera will automatically give you an error message detailing any logical loops in the project when you try to schedule it.