sub-project

Hi to all expertise

I have a situation like below

Our engineering team sits in a different country, similarly procurement, but I am at site.  In P3 ver 3.1, each phase of engineering and procurement is created as separate sub-project.  During Monitoring Engineering team updates the sub-project , similarly procurement did the same, since I hold the masterproject, I just pull the sub-project of engineering and procurement through interface to update the master project. This avoids Master project being mishandled by any of the consultant or sub-contractor.

 

Is there any such process in P6 ver.7, since  I am sending the whole master project to all, this make me more transparent to all my consultant and sub-contractor, which I dont want.  Can anyone help me

 

Thanks

Narayanan

N
narayanan venkat 👤 Member for 19 years 3 months

Hi Daniel

thanks for your suggestion, I did using project portfolio, but the main problem is every week we update schedule, all subprojects gets linked through activity ids to the masterproject, so deleting old subproject and pulling the new updated subproject doesn't disturb the master schedule in P3, but in P6 I tried 3 separate projects, linked through portfolios, but when I try to delete one of the old project and pull the updated project, all the links to the another project in the porfolio is gone, can you suggest me a way.

I hope I tried to convey my message.

 

Thanks

Narayanan

D
Daniel Limson 👤 Member for 24 years 7 months

Hi Narayanan,

P6 has the equivalent feature. Look and study on how to manage Portfolios.

Best regards,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts