Getting the hours out of P6

2 replies [Last post]
Martyn Coates
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 8 Aug 2007
Posts: 32

Hi

 

This is simple stuff but I seem to have fogotten and cant find anything in the forum  giving exactly the info I need.

I'm pretty new to P6 resources and have a loaded schedule per discipline and I want to take the hours out to produce an S curve.

I want to take hours out by resource over time with actual then budgeted.

The info looks like what you get when you view the resource usage spreadsheet. I used to just copy and paste that into excel from P5 but P6 wont let me do it.

I cant seem to get a report to get the info out in the same way.

 

Help

Replies

Martyn Coates
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 8 Aug 2007
Posts: 32

Thanks AP PM but this doesnt work.

I cant seem to copy and then paste into excel. If I go to edit, the copy / paste is unavailable to select.

I have always done this without the messing about with running reports. I have 6.0 and aware of some glitches - is this one of them?

Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Martyn,

Go to Resource Assignment Window, group the activities according to your requirements and at the right pane, show the actual & budgeted units. When done, Edit --> Select All, right click copy & paste it to Excel.

Regards.